Continuing from the previous session, we proceeded with the ceiling work.
In the meantime, we also built the foundation for the window side.


Caulk the gaps between the boards and apply aluminum tape over them.
Finally, the plasterboarding of the ceiling was completed.
Two days were spent on the ceiling work alone.


The next step is to work on the walls.
We installed sound absorbing material on all surfaces.

The same work was done on the entrance side.
After this, we would put two layers of sound absorbing material on the entire surface.