Sprint target: polish 1.4 Beta then release 1.4Days worked: 1 | Pomodoros logged: 8Task points completed: 0/168
Day 1 of the new sprint. I used it mainly for organisation: I briefed Victoria on the art requirements and worked out a plan for the relationship tables with Hyneman.
One of the big things I learned during the last sprint was not to leave a big content writing task until the end of the sprint, so I created a content plan in which I'll add NPCs to the relationship tables during every dev day. I added 32 today, and also set up a crowdsourcing post to get NPC ideas from the community.
I have meetings for my real job all day tomorrow and Thursday, so the next dev day will be Friday. See you guys then.
Link to the Trello