[STATUS] - March 2018 (Update March 29th, 8:00pm AEST) (Patreon)
Downloads
Missing 9 full-res photos, 1 file, as this post has not yet been imported.
Content
The pivot and inside shoulder bearing for the Saros Pointer Assembly - There were several other adjacent components constraining the size, shape and design of this little bearing. This was the ancient solution to permit not only clearance from those other components, but also to provide vertical stability and acceptable friction: (Short Video)
-----------------------------
(Update March 28th, 12:00pm AEST)
The new Weiss lathe (WM250VF) has been sitting idle in the shop without being properly installed for many months due the the AM and BSC projects, but I finally got around to leveling it and taking first cuts over the last few days. First impressions so far: Its a high quality machine, with not a whole lot to complain about. I'll cover it detail in the next TGT, but I want to push it a bit harder over a few weeks to make sure I don't miss anything before discussing. So I will do a bit more on that TGT today, and then back on the AM from tomorrow, working on both over the next few weeks.
-----------------------------
(Update March 23rd, 8:00pm AEST)
I've had a blast writing and narrating this latest vid, and I think its going to kick off a fun new series - the first episode is on its way to you now, and it should land in a few hours.
-----------------------------
(Update March 21st, 11:00am AEST)
Putting in a safe edge as part of the new shop skills video series - more editing today
-----------------------------
(Update March 17th, 6:15pm AEST)
I started shooting today for the new series of shop skills vids - I've decided to kick it all off with my fave tool: hand files
-----------------------------
(Update March 13th, 7:15pm AEST)
The pivot supporting structure for this next part of the mechanism (Saros train) is most unconventional by modern standards - this is part of the small bearing insert that will hold the Saros Pointer assembly. A thin flange will slip over the smaller square boss, and then the whole thing will be riveted into the main plate, much like the main bearing.
-----------------------------
(Update March 8th, 6:15pm AEST)
The test fit is good - all ready for permanent riveting.
-----------------------------
(Update March 7th, 5:15pm AEST)
A square hole for the F assembly hub - I do wonder who got the job of filing these on the original...
-----------------------------
The chips have officially started to fly on episode 7 of the Antikythera build - if you're interested in following the progress of this and other videos throughout the month, this is the link to visit with short updates posted every few days - Also a good place to post any questions etc - Cheers :)
Files